Our First Home

Thursday, 20 December 2012

Landscaping - Day 7



Posted by Servicelocator at 8:55 am No comments:
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest

Wednesday, 12 December 2012

Landscaping - End of Day 1

Some pics after Day 1 of the landscaping




Posted by Servicelocator at 9:18 am No comments:
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest

Landscaping - Before






Some pics around the house before the landscaping
Posted by Servicelocator at 9:16 am No comments:
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Newer Posts Older Posts Home
Subscribe to: Posts (Atom)

Construction Timeline

2012-07-30 - Handover
2012-07-23 - Interim Occupancy certificate
2012-07-18 - Independent inspection
2012-07-16 - PCI
2012-07-12 - Interim Occupancy Inspection
2012-07-11 - Kitchen Splashback
2012-07-10 - Driveway
2012-07-06 - Fly screen
2012-07-05 - Driveway formed up
2012-06-29 - Door Handles
2012-06-28 - Painting completed
2012-06-27 - Letter informing PCI
2012-06-19 - Internal Painting final coat
2012-06-13 - Ground floor tiling completed
2012-06-08 - Ground floor tiling started
2012-06-07 - Electrical fixes
2012-06-05 - More Plumbing
2012-05-29 - Painting Start
2012-05-23 - Internal fixes
2012-05-22 - Wet area tiling completed
2012-05-16 - Wet area tiling start
2012-05-15 - Wet area doors
2012-05-11 - Kitchen cupboards
2012-05-10 - Waterproofing
2012-05-09 - Staircase
2012-05-08 - Lockup
2012-05-03 - Lining Completed
2012-04-18 - Internal Lining
2012-04-13 - Insulation
2012-04-03 - Cladding
2012-04-01 - Frame, indépendant Inspection
2012-03-30 - Electrical Rough In
2012-03-20 - Lower roof
2012-03-16 - Scaffoldings removed
2012-03-14 - Eaves installed an painted
2012-02-15 - Brickwork Completion
2011-12-22 - Frame Completion
2011-12-03 - Slab
2011-11-10 - Site cut for the slab

Pre-construction Timeline


2011-11-02 - Signing the final documents
2011-10-07 - DA Approval
2011-09-18 - Electrical Appointment
2011-09-09 - Plan submission to the DA
2011-08-31 - Approval from the DRB
2011-08-24 - Kitchen Appointment
2011-08-18 - Plan submission to the DRB
2011-08-06 - Colour Selection
2011-07-21 - Contract Signing
2011-05-13 - Tender presentation
2011-02-27 - Initial deposit




Total Pageviews

Followers

Blog Archive

  • ►  2013 (1)
    • ►  January (1)
  • ▼  2012 (29)
    • ▼  December (3)
      • Landscaping - Day 7
      • Landscaping - End of Day 1
      • Landscaping - Before
    • ►  July (1)
    • ►  June (6)
    • ►  May (2)
    • ►  April (3)
    • ►  March (4)
    • ►  February (8)
    • ►  January (2)
  • ►  2011 (4)
    • ►  December (2)
    • ►  August (1)
    • ►  May (1)

About Me

Servicelocator
View my complete profile
Awesome Inc. theme. Powered by Blogger.